Talk to TopKlanDespite detailed advice from the consultants the contractor failed to build the services coordination designs before casting. The designs needed coordination with architecture and civil drawings before proceeding.
Several electrical loads were shutting down repeatedly due to frequent circuit breaker tripping. Investigation revealed:
. All automated loads were connected to a sign phase.
. A 32A SPN breaker was required, but a 100A SPN breaker had been installed, leading to overload.
Feedback based on real coordination challenges and real project outcomes.
We're happy to discuss your project, review your requirements, or help resolve specific electrical coordination or system challenges.